Current Projects

 

Fullhurst Community College - Phase 2

Phase 1 of Fullhurst has been completed and work has commenced on Phase 2.

Phase 2 will be completed for handover at the start of September 2009, with most of the demolition work scheduled to take place during the School holidays, significantly reducing the impact on education within the school. The existing village of mobile classrooms will also be removed over the summer holidays with the whole school located in the new buildings from the beginning of the Autumn term.

Advance work in the Summer of 2008 plus re-programming and acceleration of the construction works has resulted in the building contractors finishing on site in September 2009 instead of the programmed June 2010 completion date.

read more

Completed Projects

Soar Valley College

BREEAM Rating Excellent

This 100% new-build project, the largest of the phase 1 schools, opened on the 1 st June 2009.

The completed school includes:

  • An allotment area, an ecology garden and external teaching areas next to the art rooms
  • Improved and enhanced sporting facilities including a new sports hall, aerobics/dance area and fitness suite
  • Flexible teaching areas
  • Enhanced ICT capabilities


read more

Judgemeadow Community College

Judgemeadow Community College

"Working together to ensure the highest quality education for each individual pupil through a culture of continual improvement"

Inclement weather hindered production at the start of the project, but with good management and attention to programme interfaces, the opening date was still achieved. Judgemeadow was handed over on 1 st June 2009.

Judgemeadow benefits from design which allows the space to be flexible, creative and dynamic.

read more

Beaumont Leys School

Beaumont Leys Secondary School

LMEC have successfully delivered a complete new-build solution for Beaumont Leys School, which opened six weeks ahead of schedule on the 20 th April. This is the first BSF School in the country to complete ahead of schedule.  

The exciting new building has already attracted positive attention, being branded the 'school of many colours' due to the use of pinks, blues, greens, yellows and purples on the walls and floors throughout the building.

A strong working relationship has led to praise from Liz Logie, Headteacher:

"The facilities that Leicester Miller has delivered are amazing…they have really created a new learning environment…but right throughout the build, the site manager was always on call and couldn't do enough to help. There were very few interruptions to learning as a result of the building going on.   They were great! Real partners who couldn't do enough and knew that what they were building was more than bricks and mortar…it would change a Community."

read more